The invention relates to a method for constructing an 
engineering pile by combining a rotary drilling rig with manual 
pile base chambering, which comprises the following steps: (1) preparation work before construction, including field leveling; (2) 
pile lofting; (3) pile casing embedding; (4) rig installation and rotary drilling; (5) manual pile base chambering; (6) rotary drilling 
drill quality detection; (7) reinforcement cage manufacturing; (8) reinforcement cage installation; (9) preparation before 
casting, mainly including hole cleaning, final hole acceptance check, and pump concrete 
casting quality safeguard measure; and (10) concrete 
casting, mainly including guide 
pipe installation, concrete casting and sampling for test and pile forming. In the method for constructing the 
engineering pile by combining the rotary drilling rig with the manual pile base chambering, the high efficiency of the rotary drilling rig is fully utilized, and the manual pile base chambering is utilized, the advantages of the rotary drilling rig and the manual pile base chambering are combined to make up the defects of the rotary drilling rig and the manual pile base chambering. The construction steps are detailed; the process flow is clear and definite; the construction quality of the 
engineering pile is ensured through an effective detail measure; the construction process of the rotary drilling rig and the process step of the manual pile base chambering are combined as a whole to realize the effective allocation of a construction field, a construction 
machine and construction time; and when the construction quality is ensured, the construction efficiency of a digging pile is greatly increased, thereby, the construction time of the engineering pile can be greatly saved, and the construction period requirement of the project is met.