The invention discloses a construction method of a gravel grouting 
pile. The construction method comprises the following steps: (1) preparing for construction, (2) conducting measurement, paying off and positioning of the 
pile, (3) embedding a protective canister, (4) placing a drilling 
machine in place, (5) forming a hole by drilling, (6) cleaning the hole at a time, (7) placing a grouting 
pipe, (8) placing an anchor bar, (9) putting gravels in the hole, (10) installing a 
pile cap connecting steel 
pipe, (11) cleaning the hole, (12) conducting 
pressure grouting, (13) pulling the grouting 
pipe out, (14) constructing a 
pile cap, and (15) conducting detection and acceptance inspection on the finished pile. According to the construction method of the gravel grouting pile, the construction speed is high, the construction period is shortened, and compared with soft foundation treatment such as a prestressed pipe pile and a Y-type pile, the 
engineering investment is saved; the labor intensity is low, the construction is safe, and the construction method can be widely popularized and used; the gravel pile formed by 
cement and gravels is high in integrality and stability. The 
engineering drilling 
machine is adopted in a soft foundation to 
drill the hole in a rotating and 
cycling mode to form the pile, the disturbance to the foundation and the surrounding buildings is small, ground depression is controlled, and the construction method is small in vibration and low in 
noise during the construction and has good 
social benefits.