The invention specifically relates to an elevated trestle bridge construction method on covering-free steep bare rock in deepwater and rapid 
stream. A scheme of the invention is as follows: the elevated trestle bridge construction method comprises the following steps of: constructing a first porous trestle bridge on the 
bank, then constructing a second porous trestle bridge by adopting a 
cantilever method, and arranging guide frames on the 
tail end part of the second porous bridge; 
settling cut steel 
pipe piles in mounting sites, then 
casting an 
underwater concrete layer in the steel 
pipe piles, and drilling an anchor hole along the central axis direction of each steel 
pipe pile after the 
underwater concrete layer is cured, wherein each anchor hole penetrates through the 
underwater concrete layer and extends into 
basement rock of a 
river bed; and finally arranging an 
anchor bolt in each anchor hole, grouting and anchoring, then assembling a truss to form a third porous trestle bridge, and repeating the steps till finishing the construction of the whole trestle bridge. The elevated trestle bridge construction method disclosed by the invention has the advantages of reducing the 
deep diving operation load and the construction risk by adopting an underwater exploration technology in combination with precutting of a bottom opening of each steel pipe 
pile on the 
bank, enabling each steel pipe 
pile to be firmly anchored on the steep bare rock surface by adopting the 
anchor bolt grouting and rock-socketing technology between the steel pipe pile and the steep bare rock surface, shortening the construction peroiod and reducing the construction cost.